• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to footer

Tams Group

Marine Services, Integrated Marine, Perth Vessel Operator, Tugs, Commercial Diving, Dredging, Marine Manning, Fremantle Shipyard, Onslow Shorebase

  • info@tamsgroup.com.au
  • +61 8 9430 5889
  • Projects
  • Services ▿
    • Marine Manning
    • Harbour Tug Services
    • Synthetic Fibre Ropes
    • Commercial Diving
    • Marine Construction Australia
    • Pile Protection and Repair
  • Fleet
  • Shore Bases ▿
    • Fremantle Shore Base
    • Port Hedland Shore Base
    • Onslow Shore Base
    • Gladstone Shore Base
  • Equipment
  • About ▿
    • Sustainability & Community
  • News
    • Announcements
  • Employment
  • Contact

FMG T155 Sheet Pile Wall Installation

Total AMS were contracted by Fortescue Metals Group to install 125 No. 1200OD interlocking piles in South West Creek to form a retaining wall thereby permitting dredging to occur within 10m of their existing infrastructure at the Herb Elliot Port.

Total AMS utilised a 350t payload jackup barge, 240′ crane barge equipped with a 650t crane and an IHC S-280 piling hammer to install the piles up to 35m into the seabed.  Some piles were drilled with a pile top drill rig to progress the piles beyond refusal at specific locations.  The project duration was 6 months and required a crew of 40 people.

gallery gallery
  • Project Info

    Client
    Fortescue Metals Group
  • Location
    Anderson Point, Port Hedland
  • Duration
    6 months
  • Download

    Download Fact Sheet pdf 699.96 KB

Do have questions about our Marine & Construction Projects?

Contact Us today and let's have a chat

sidebar

Footer

12 Rous Head Road, North Fremantle, WA, 6159
+61 8 9430 5889
info@tamsgroup.com.au





© TAMS Group
Website Perfected by:Be Media&Tangelo Creatives
Cleantalk Pixel